Net Metering
Net metering in Pakistan 2026: the rules and the buyback rate now
Net metering closed to new users on 9 Feb 2026. New solar gets net billing at about Rs 10 to 11 a unit on 5-year contracts; old contracts keep their terms.
Net Metering · Solar
The net metering process: apply on PITC's portal (nmp.pitc.com.pk) or with K-Electric. Steps, documents, fees and the DISCO deadlines (about 56 working days).
AI Summary
New solar connections in Pakistan get net billing, not net metering, since 9 Feb 2026, but the application works the same way. For LESCO, IESCO and nine other DISCOs, you or your installer apply on PITC's portal, nmp.pitc.com.pk. Your system can't be bigger than your sanctioned load. Up to 25 kW there is no NEPRA fee; above that it is Rs 1,000 per kW. You pay the DISCO's estimate for the meter, and its deadlines add up to about 56 working days.
The net metering process starts online: you or your installer apply on PITC’s online portal, nmp.pitc.com.pk, if your DISCO is LESCO, IESCO or one of nine other government DISCOs. Since 9 Feb 2026, new connections get net billing, not net metering, but the steps are the same. Your system can’t be bigger than your sanctioned load. NEPRA’s deadlines for the DISCO add up to about 56 working days.
Not for new applications. NEPRA’s Prosumer Regulations 2026, notified on 9 February 2026, replaced the 2015 net metering rules with net billing. Units you take from the grid are billed at your normal tariff, and units you send are credited at the national average energy purchase price. Contracts run five years.
If you applied by 8 February 2026, your case stays under the old net metering rules, as The Nation reported on 3 April 2026. What the switch means for your bill is in our net metering rules and buyback rate guide.
To raise your sanctioned load, apply on the ENC portal (enc.com.pk). Some MEPCO, IESCO and FESCO areas use the Power Smart app or a customer facilitation centre instead.
The forms come free from the portal, and the DISCO must give you NEPRA’s documents free within 2 working days if you ask.
| Cost | Who you pay | Amount |
|---|---|---|
| Forms and documents | DISCO | Free |
| NEPRA fee, up to 25 kW | None | Rs 0 since April 2026 |
| NEPRA fee, above 25 kW | NEPRA | Rs 1,000 per kW, once |
| Meter and connection | DISCO (demand notice) | Set by the DISCO’s estimate |
You pay all costs of connecting up to the meter point, including the meter. If the DISCO has no meters in stock, NEPRA’s rules let you buy one yourself, and the DISCO tests it before fitting. We found no official DISCO price for the meter, so we don’t quote one.
Up to 25 kW, yes. As first notified, the 2026 regulations needed NEPRA approval and Rs 1,000 per kW for every system. Dawn reported on 28 April 2026 that NEPRA dropped the licence and fee for systems up to 25 kW, backdated to 9 February 2026. The Nation reported on 7 August 2026 that DISCOs now approve these systems directly.
We couldn’t open the amended text on NEPRA’s website, which blocks automated access, so this follows the news reports.
The deadlines in NEPRA’s regulations add up to about 56 working days, or roughly 11 weeks, if nothing is missing:
| Stage | Deadline |
|---|---|
| DISCO confirms the file is complete | 5 working days |
| Technical review | 15 working days |
| Agreement signed | 7 working days |
| Estimate (demand notice) issued | 7 working days |
| You pay | 7 working days |
| Meter installed | 15 working days |
Under AEDB rules, your installer must get DISCO approval within 120 days of your customer agreement, and tell you in writing if there’s a delay. Deadlines are not always met: the Power Division said on 6 September 2026 that 4,959 applications from the switchover were still being verified.
Use Search Application on nmp.pitc.com.pk. If you applied on the earlier Step Robotics system, your case is still tracked there. Pre-February cases under verification can be checked at nmverification.pitc.com.pk, according to the Power Division. The portal also lists a net metering contact person for each DISCO, and general queries go to [email protected].
More guides: Net Metering, net metering rules and rates, solar system prices, what size system you need, is solar worth it under net billing, solar loans and instalment plans.
For LESCO, IESCO, FESCO, GEPCO, MEPCO, PESCO, HESCO, SEPCO, QESCO, TESCO and HAZECO, apply on PITC's portal at nmp.pitc.com.pk, yourself or through your installer. Applications made since 9 Feb 2026 get net billing, not net metering.
A copy of your CNIC, the signed NEPRA Schedule II application form with a one-line diagram, inverter details and a site plan, the signed interconnection agreement, and your installer's customer agreement under AEDB rules.
There is no NEPRA fee for systems up to 25 kW, as reported in April 2026. Above 25 kW you pay NEPRA Rs 1,000 per kW once. You also pay your DISCO's estimate for the meter and connection.
NEPRA's regulations give the DISCO deadlines that add up to about 56 working days from application to commissioning, if your file is complete. That is roughly 11 weeks.
Use Search Application on nmp.pitc.com.pk. Older cases filed before 9 Feb 2026 that are still being verified can be checked at nmverification.pitc.com.pk.