Net Metering · Solar

How to apply for net metering in Pakistan, step by step (now net billing)

The net metering process: apply on PITC's portal (nmp.pitc.com.pk) or with K-Electric. Steps, documents, fees and the DISCO deadlines (about 56 working days).

Apply on
nmp.pitc.com.pk
NEPRA fee
None up to 25 kW
Max system
Your sanctioned load
DISCO deadlines
About 56 working days
Summarize it for me

AI Summary

New solar connections in Pakistan get net billing, not net metering, since 9 Feb 2026, but the application works the same way. For LESCO, IESCO and nine other DISCOs, you or your installer apply on PITC's portal, nmp.pitc.com.pk. Your system can't be bigger than your sanctioned load. Up to 25 kW there is no NEPRA fee; above that it is Rs 1,000 per kW. You pay the DISCO's estimate for the meter, and its deadlines add up to about 56 working days.

The net metering process starts online: you or your installer apply on PITC’s online portal, nmp.pitc.com.pk, if your DISCO is LESCO, IESCO or one of nine other government DISCOs. Since 9 Feb 2026, new connections get net billing, not net metering, but the steps are the same. Your system can’t be bigger than your sanctioned load. NEPRA’s deadlines for the DISCO add up to about 56 working days.

From application to a working meter
  1. You or installer Apply on nmp.pitc.com.pk Forms, CNIC, system details
  2. DISCO Review and agreement 5 + 15 + 7 working days
  3. You Pay the estimate Meter and connection cost
  4. DISCO Install the meter Within 15 working days

Is it still called net metering?

Not for new applications. NEPRA’s Prosumer Regulations 2026, notified on 9 February 2026, replaced the 2015 net metering rules with net billing. Units you take from the grid are billed at your normal tariff, and units you send are credited at the national average energy purchase price. Contracts run five years.

If you applied by 8 February 2026, your case stays under the old net metering rules, as The Nation reported on 3 April 2026. What the switch means for your bill is in our net metering rules and buyback rate guide.

Who can apply?

  • Three-phase consumers. NEPRA’s standard agreement says the applicant must be a three-phase 400V or 11 kV consumer of the DISCO.
  • Sanctioned load of at least 5 kW. PITC’s portal won’t accept you with a single-phase connection or a load under 5 kW until you apply for a change of load.
  • System no bigger than your sanctioned load. A 10 kW sanctioned load allows at most a 10 kW system. See what size solar system you need.
  • Room on your transformer. The DISCO can’t accept your application if solar on your local transformer has reached 80% of its rating. Check this first with “Check Transformer Overloading” on the portal.

To raise your sanctioned load, apply on the ENC portal (enc.com.pk). Some MEPCO, IESCO and FESCO areas use the Power Smart app or a customer facilitation centre instead.

What is the net metering process, step by step?

  1. Choose an AEDB-certified installer and sign a customer agreement on stamp paper before work starts. Under AEDB rules it lists your equipment and warranties, including 10 years on panels and 5 years on grid-tie inverters. Inverters must meet the UL 1741 standard. Prices are in our solar system price guide.
  2. Check your sanctioned load and transformer on nmp.pitc.com.pk. Raise your load through ENC first if you need to.
  3. Download and fill the forms from the portal: the interconnection agreement between DISCO and consumer, and NEPRA Schedules II to V. Sign them, and have your installer sign Schedule II.
  4. Submit the application on nmp.pitc.com.pk with “Apply For Net Billing (By Consumer)”, then pick your installer. The installer adds the inverter and panel details, uploads the documents and submits. Or the installer applies for you with “(By Installer)”, which goes straight to the DISCO field office.
  5. Answer the DISCO. Within 5 working days it tells you whether the file is complete. You then have 3 working days to send anything missing.
  6. Wait for the technical review. The DISCO has 15 working days to check whether your system can connect. If it can’t, it returns the file with reasons within 3 working days.
  7. Sign the agreement with the DISCO, due within 7 working days of approval.
  8. Pay the estimate. Within 7 working days of signing, the DISCO issues a demand notice for the connection and meter. You pay it within 7 working days.
  9. Get the meter installed. The DISCO installs and commissions the connection within 15 working days of payment. Your bill then moves to net billing.

What documents are required?

The forms come free from the portal, and the DISCO must give you NEPRA’s documents free within 2 working days if you ask.

  • Copy of your CNIC (or company registration number, the CUIN)
  • Schedule II application form: your consumer reference number, whether you own or lease the property, expected yearly use and production in units, installer details and the date you want to connect
  • One-line schematic diagram of the system
  • Inverter details: make, model, serial number, phase and AC rating
  • Site plan showing the outside disconnect switch. NEPRA requires a manual switch with a visible break.
  • Signed interconnection agreement (Schedule I)
  • Installer’s customer agreement and undertaking under AEDB rules
  • Above 25 kW: Schedules III and V and the NEPRA fee. At 250 kW or more: a load flow study by the DISCO or a Pakistan Engineering Council-registered consultant.

How much does it cost?

Cost Who you pay Amount
Forms and documents DISCO Free
NEPRA fee, up to 25 kW None Rs 0 since April 2026
NEPRA fee, above 25 kW NEPRA Rs 1,000 per kW, once
Meter and connection DISCO (demand notice) Set by the DISCO’s estimate

You pay all costs of connecting up to the meter point, including the meter. If the DISCO has no meters in stock, NEPRA’s rules let you buy one yourself, and the DISCO tests it before fitting. We found no official DISCO price for the meter, so we don’t quote one.

Was the Rs 1,000 per kW fee dropped?

Up to 25 kW, yes. As first notified, the 2026 regulations needed NEPRA approval and Rs 1,000 per kW for every system. Dawn reported on 28 April 2026 that NEPRA dropped the licence and fee for systems up to 25 kW, backdated to 9 February 2026. The Nation reported on 7 August 2026 that DISCOs now approve these systems directly.

We couldn’t open the amended text on NEPRA’s website, which blocks automated access, so this follows the news reports.

How long does net metering take?

The deadlines in NEPRA’s regulations add up to about 56 working days, or roughly 11 weeks, if nothing is missing:

Stage Deadline
DISCO confirms the file is complete 5 working days
Technical review 15 working days
Agreement signed 7 working days
Estimate (demand notice) issued 7 working days
You pay 7 working days
Meter installed 15 working days

Under AEDB rules, your installer must get DISCO approval within 120 days of your customer agreement, and tell you in writing if there’s a delay. Deadlines are not always met: the Power Division said on 6 September 2026 that 4,959 applications from the switchover were still being verified.

How do I check my application status?

Use Search Application on nmp.pitc.com.pk. If you applied on the earlier Step Robotics system, your case is still tracked there. Pre-February cases under verification can be checked at nmverification.pitc.com.pk, according to the Power Division. The portal also lists a net metering contact person for each DISCO, and general queries go to [email protected].

LESCO, IESCO and K-Electric: what’s different?

  • LESCO, IESCO and the other government DISCOs (FESCO, GEPCO, MEPCO, PESCO, HESCO, SEPCO, QESCO, TESCO, HAZECO) all use the same PITC portal. LESCO moved its 1,204 pre-February applications to PITC and handles new ones through the net billing portal, The News reported on 24 June 2026.
  • K-Electric in Karachi isn’t on the PITC portal. The same NEPRA regulations and deadlines apply to it. KE’s website blocked us when we tried to check its application page in October 2026, so ask KE directly for its form and document list.

More guides: Net Metering, net metering rules and rates, solar system prices, what size system you need, is solar worth it under net billing, solar loans and instalment plans.

Questions people ask

How do I apply for net metering online?

For LESCO, IESCO, FESCO, GEPCO, MEPCO, PESCO, HESCO, SEPCO, QESCO, TESCO and HAZECO, apply on PITC's portal at nmp.pitc.com.pk, yourself or through your installer. Applications made since 9 Feb 2026 get net billing, not net metering.

What documents are required for net metering?

A copy of your CNIC, the signed NEPRA Schedule II application form with a one-line diagram, inverter details and a site plan, the signed interconnection agreement, and your installer's customer agreement under AEDB rules.

What is the net metering fee in Pakistan?

There is no NEPRA fee for systems up to 25 kW, as reported in April 2026. Above 25 kW you pay NEPRA Rs 1,000 per kW once. You also pay your DISCO's estimate for the meter and connection.

How long does net metering take?

NEPRA's regulations give the DISCO deadlines that add up to about 56 working days from application to commissioning, if your file is complete. That is roughly 11 weeks.

How do I check my net metering application status?

Use Search Application on nmp.pitc.com.pk. Older cases filed before 9 Feb 2026 that are still being verified can be checked at nmverification.pitc.com.pk.

Sources

  1. NEPRA (Prosumer) Regulations, 2026 (S.R.O. 251(I)/2026), NEPRA (accessed 10 Oct 2026)
  2. Net Metering / Net Billing Portal, PITC (accessed 10 Oct 2026)
  3. Guidelines for Installers: Net Billing Portal Usage, PITC (accessed 10 Oct 2026)
  4. Net Metering data flow diagram, PITC (accessed 10 Oct 2026)
  5. NEPRA Schedules II to V (application form, concurrence, fee, affidavit), PITC / NEPRA (accessed 10 Oct 2026)
  6. AEDB (Certification) Regulations 2021, Schedules 3 and 4, PITC / AEDB (accessed 10 Oct 2026)
  7. Nepra abolishes licence requirement, fee for small solar users, Dawn (accessed 10 Oct 2026)
  8. Nepra scraps requirement for license for small-scale prosumers using up to 25 kW, The Nation (accessed 10 Oct 2026)
  9. Nepra pulls the plug on net-metering, Dawn (accessed 10 Oct 2026)
  10. Reversing earlier decisions, Nepra exempts pre-Feb 9 prosumers from new regulations, The Nation (accessed 10 Oct 2026)
  11. Nearly 11,700 net metering cases resolved, Express Tribune (accessed 10 Oct 2026)
  12. Lesco leads Discos with 2,053MW net metering capacity, The News (accessed 10 Oct 2026)